Construction at the Google data center project in Botetourt County must stop, a circuit judge ordered Monday, after ruling that the county’s board of supervisors violated Virginia’s Freedom of Information Act when it approved a key agreement with the tech giant.
All actions the county has taken since the June 24, 2025, meeting greenlighting the project are rescinded, and the county must hold a public hearing on the matter that “conforms to” the state law regarding open meetings and open records, substitute Judge Michael Doucette wrote.
Robert Dallas filed the suit Nov. 2, alleging that the board of supervisors did not disclose on its published agenda that it would be discussing a performance agreement with Google’s developer, Helio Capital LLC, or a resolution to enact the agreement in a closed meeting.
After the board returned to public session, it voted 5-0, with no discussion, to approve the agreement, but only after it added the item to its agenda during the meeting, Dallas alleged. It only publicized what it had voted on hours later.
A lawyer for the county did not dispute those facts but argued that the county did enough to satisfy state law.
During arguments in Botetourt County Circuit Court on Nov. 10, Julian Harf — representing the county, the board and the economic development authority — “stated on a number of occasions that the alleged violations … were ‘technical violations’ and on one occasion stated that ‘magic words’ were not used,” Doucette wrote to parties in the case.
“Such concessions are precisely the point” that Dallas raised, the judge added. “The state’s FOIA “is a technical and strictly procedural act adopted by the General Assembly. ‘Magic words’ must be used and ‘technical violations’ are not excused.”
Dallas’ legal team, led by Roanoke-based attorney John Fishwick, said in a prepared statement that it is pleased with the decision.
“We believe this result sends a clear message to public bodies throughout the commonwealth, that the rule of law and the public’s right to witness and participate in government must be respected,” the statement read.
Fishwick said in an email that the team would not comment beyond its press statement.
Botetourt County spokesman Brent Watts said in an email to media that county leaders would review the ruling with staff and the board and will not do interviews but will “share updates as appropriate” on the matter, which remains in litigation.
“The county respects the legal process and appreciates the attention the court gave to hearing this matter,” read a statement that Watts emailed. “The county … is evaluating its options going forward.”
Work continued at the Botetourt Center at Greenfield site at least 40 minutes after the county issued its 3:36 p.m. statement.
[Disclosure: Google is one of our donors through its Google News Initiative, which helped support our expansion in the New River Valley. Donors have no say in news decisions; see our policy.]
This is a breaking story that will be updated.