Efforts remain underway to start up factories in Wythe County to make medical rubber gloves and their raw material, a project that was first announced in late 2021 with the expectation of bringing 2,500 jobs to the county but which has since stalled due to a lack of funding.
Further developments since Cardinal News first reported on the projectโs financial challenges in August reveal that a number of manufacturers of personal protective equipment are in a similar situation as Blue Star NBR, the company behind the project.
Blue Star NBR โ the โNBRโ stands for nitrile butadiene rubber โ used $123 million in federal funding to build a factory capable of producing 90,000 tons of rubber annually to make gloves such as those commonly seen in hospitals and doctorsโ offices. The company needs about $230 million to build a second factory, staff both plants and start making billions of gloves each year, CEO Scott Maier has said.
Blue Star had expected to use a pandemic-related federal loan package to finish the task, but the deal never closed and progress on the factory project came to a halt. Now, Maier hopes to convince lawmakers to include Blue Star in the federal budget, most likely using money from the U.S. Department of Health and Human Services.
โWeโre continuing our lobbying efforts to raise awareness in Congress as to what the issue is,โ Maier said. โI think what we found was most of the members we talked to, both in the Senate and in the House [of Representatives], werenโt aware that the entire effort had stalled, and it wasnโt just our company but this is an industrywide problem.โ
In September, Maier and 17 other executives of medical-supply companies signed an open letter lamenting that the federal government โabandonedโ its pandemic-era commitment to boosting the domestic manufacturing of gloves, gowns, masks and other PPE.
The letter was shared with congressional and White House staff and entered into the congressional record during a U.S. House Committee on Energy and Commerce hearing on domestic manufacturing, China and supply chains.
โWhile the U.S. Government made a roughly $1 billion down payment to bolster domestic PPE manufacturing capacity during the height of the COVID-19 pandemic, the effort has stalled and this initial investment has been put in jeopardy,โ the letter stated.
Lacking a reliable supply of PPE could harm public health, the letter stated.
Furthermore, the letter stated, boosting domestic PPE supply is critical because of Chinaโs โunfair business practicesโ โ an allusion to accusations that Chinese companies sell gloves at artificially low prices to increase market share โ while Malaysia, another major source of medical PPE, has a โhistoric used of forced laborโ that has caused supply chain disruptions due to rules prohibiting imports made with such labor.
The letter urged Congress and the U.S. executive branch to “complete the job they started” and fully fund the various domestic PPE manufacturing projects.
“Lives should not be put at risk due to a failure to complete this worthy mission,” the letter stated.
Maier said in an interview that with the U.S. so dependent on imported PPE, it wouldnโt even take another global pandemic to threaten the supply.
โAll it needs to be is a supply chain disruption where you canโt get boats from the Far East to here,โ Maier said.
In August, Cardinal News reached out to the offices of U.S. Sen. Mark Warner, D-Virginia; U.S. Sen. Tim Kaine, D-Virginia; and U.S. Rep. Morgan Griffith, R-Salem, about the Blue Star project.
At that time, the three lawmakers said in a joint statement that they had teamed up to urge the Biden administration and Blue Star to come to an agreement to get the plant on track and were โdisappointed that an agreement was not reached.โ
This month, a Kaine spokesperson said that there was nothing new to share.
David Manley, executive director of the Joint Industrial Development Authority of Wythe County, said he feels there is โan increasing momentum to finding a workable solution for this, and we remain optimistic.โ
โThere is a concerted effort being made by Blue Star and various industry partners to work with the federal government to come up with a solution that will not only kick this production into gear but make us more resilient as a nation,โ Manley said.
Maier also said he is optimistic that a solution will be found.
โEvery person we talk to is like, โOh, we thought [Health and Human Services] took care of this a couple years ago,โโ Maier said. โWell, it started, but unfortunately it stalled, and we need some sort of help to get it un-stalled.โ
Blue Star has looked into private investment, but it presents a chicken-and-egg problem: Private investors wonโt buy in until thereโs sufficient demand for the raw rubber, but there wonโt be sufficient demand until Blue Starโs own glove-making factory gets going, Maier said.
Meanwhile, the one Blue Star NBR factory that has been constructed sits idle in Wythe County. The chemicals that were there have been put in storage.
โWe only brought in a small amount to operate the pilot plant when we were proving out that the NBR formula works. Weโve taken all the chemicals offsite and itโs just the equipment thatโs sitting there,โ Maier said.
Blue Star has spent $3 million to $4 million in preventative maintenance and upkeep on the plant and its equipment, including about $250,000 last month to winterize the facility, Maier said.
โWeโve likened it to, you canโt just let a car sit in a garage and not do anything to it and expect it to start right up 18, 24 months later,โ he said.
This isnโt what company executives and government officials anticipated when the Blue Star project was announced to great fanfare in late 2021 and then-Gov. Ralph Northam called it โtransformational for all of Southwest Virginia.โ
Along with the jobs announcement came the news that Virginia had committed $8.5 million to upgrade water and sewer infrastructure at Wythe Countyโs Progress Park, where the factory complex is located.
Transformational or not, a basic rule of business is that if expenses keep exceeding revenue, somethingโs eventually got to give โ and Blue Star is no exception.
โItโs going to be up to our partners to decide how long we want to keep putting in money to keep this going,โ Maier said. โWeโre hopeful that the government will fix itself and fix the situation. But we canโt do it forever.โ